Exempt granny-flat construction and completion records
Collect the project evidence as work happens and prepare the council completion pack.
01/
Before construction — open one project record
Keep the PIM, people, design basis, deadlines and monitoring plan together.
-
Retain the issued PIM and application
Keep the issued PIM, Form 2AA application and everything supplied to council.
Required evidence PIM and application file
-
Record both pathways separately
Keep the Building Act exemption assessment separate from the RMA planning assessment.
Required evidence Two dated decisions
-
Identify the current design set
Record the drawings, specifications, calculations and revision that will be built.
Required evidence Dated design register
-
Record licensed people and scopes
Keep responsibility, contracts and licence or registration details for each regulated scope.
Required evidence People and scope register
-
Agree the monitoring plan
Name the checks, evidence and responsible person before work begins.
Required evidence Monitoring schedule
-
Diary the two-year PIM deadline
Set the completion deadline and an earlier decision date for any extension request.
Required evidence Project calendar entry
02/
During construction — collect evidence before it disappears
Capture covered work, variations and practitioner records as each stage finishes.
-
Take dated site photographs
Identify the location and design detail before work is covered.
Required evidence Stage photo folders
-
Retain professional monitoring reports
Keep the evidence promised in the monitoring plan without calling it a council inspection.
Required evidence Signed reports
-
Keep product and test records
Retain product information, warranties, tests and producer statements relevant to the design.
Required evidence Product evidence register
-
Approve and draw every variation
Record the instruction, reason, cost and updated drawing or specification.
Required evidence Variation register
-
Request trade records as scopes finish
Do not wait until the project deadline to collect regulated documents.
Required evidence Document tracker
03/
At completion — assemble and submit the final pack
Confirm the statutory records, accurate final plans and evidence of submission.
-
Collect applicable LBP and trade records
Obtain Records of Work and applicable plumbing, drainlaying, electrical and gas records.
Required evidence Practitioner certificates
-
Obtain design Certificates of Work
Collect the applicable certificates for restricted design work.
Required evidence Certificate or Certificates of Work
-
Make final plans match the completed work
Include every variation and the final plumbing and drainage as-builts.
Required evidence Final as-built set
-
Send the completion pack to the PIM council
Submit within the statutory period and keep evidence of receipt.
Required evidence Council receipt
-
Resolve any Form 3A payment
Record the due date and proof of payment for any development contribution.
Required evidence Payment record
-
Store the permanent owner copy
Keep final records, warranties, contracts and maintenance information together.
Required evidence Archived completion file